{keywords}
The first three-carriage train for HCM City’s Metro Line No 1, which is expected to be completed by the end of the year. — VNA/VNS Photo Tien Luc

One of the key projects is Ring Road 3 connecting provinces and cities in the Southern Key Economic Region. The road passes through HCM City and Dong Nai, Binh Duong, Long An provinces with a total length of about 89.3km.

It is expected to reduce traffic pressure on roads in the city centre, and shorten travel time between the city and provinces. However, only the first section of 16.3km, accounting for 18 per cent of the total length, has received investment.

The Government has approved a policy of compensation and resettlement for households affected by phase 1 of the Tan Van-Nhon Trach section of the Ring Road 3.

To speed up implementation, Prime Minister Nguyen Xuan Phuc assigned the Ministry of Transport to urgently complete a feasibility study on key national projects for investment policy decisions and preparation this year.

Similarly, the HCM City-Moc Bai Expressway project under a BOT contract is only in the phase of a pre-feasibility study. The 53km long expressway between HCM City and Tay Ninh will cost around VND13.6 trillion (US$568.8 million).

The Prime Minister approved the Ministry of Transport’s proposal to give the HCM City People’s Committee the authority to be in charge of making investment decisions on the expressway project. The committee has completed the pre-feasibility study and will submit it to investment authorities.

The Ministry of Planning and Investment has been asked to provide guidance on problems related to procedures for investment policy decisions, project approval, investment capital sources appraisal, and capital balance ability.

Recently, the city’s Department of Transport petitioned the People's Committee to ask the Ministry of Transport to approve building a road connecting Long Phuoc Street in District 9 with the HCM City-Long Thanh-Dau Giay Expressway.

The connecting road is expected to reduce congestion around the area and boost the economy in District 9, which is part of the planned innovative urban area in the eastern part of the city. 

Meanwhile, work on Metro Line No 1 (Ben Thanh - Suoi Tien) has reached 78 per cent completion, while Metro Line No 2 (Ben Thanh - Tham Luong) has reached 3.8 per cent completion.

The city’s People’s Committee has proposed that the Ministry of Planning and Investment consider transferring foreign capital (ODA) from the central budget that has not been disbursed this year for projects to the Metro Line No 1 next year.

It also asked the Ministry of Finance to issue a document soon to extend the disbursement period to December 20, 2026, and the loan repayment schedule to the Germany Reconstruction Bank (KFW) to September 30, 2027 for the Metro Line No 2 project. 

Long-delayed projects

Several large-scale projects have been delayed for a long time or are facing slow implementation, affecting the rights and interests of people.

For example, the Binh Quoi-Thanh Da urban area project has been delayed for more than 26 years due to prolonged site clearance and compensation issues, affecting the lives of thousands of local households. That led to one of the two investors withdrawing from the project.

Nguyen Trung Anh, deputy director of Department of Planning and Investment, said the city is taking steps to organise bidding to find new investors for the project.

Similarly, the city’s Northwest Urban Area in Hoc Mon and Cu Chi districts has become less feasible because it has not attracted many investors. The city plans to adjust the Northwest Urban Area plan and organise a contest seeking ideas for the adjustments.

Planning of the new urban area in the southern part of the city is also being adjusted in some areas with high population density, as well as design for urban space along Nguyen Van Linh Boulevard.    

The city is urgently completing its overall adjustment planning to 2040, with a vision towards 2060, and then will submit it to the Prime Minister for approval.

By merging three districts 2, 9 and Thu Duc, the city wants to create an eastern innovation urban area called Thu Duc City. It is taking steps to quickly complete planning and form the new creative city in its eastern part.   

Another planned major project is turning Can Gio District into an ecological urban area in combination with the preservation of the mangrove biosphere. The committee has asked the Prime Minister to adjust planning for Can Gio District.

The city is also developing planning for the use of urban underground spaces in the existing downtown area of 930ha and Thu Thiem new urban area in District 2.

However, the planning of underground space faces many problems related to administrative procedures and legal regulations, director of the city’s Department of Planning and Investment, Nguyen Thanh Nha, said.

To remove problems facing investors, the department has proposed that the municipal People's Committee organise a contest to choose the best planning of underground space that meets the city’s requirements, he said.  VNS 

HCM City speeds up sub-projects for smart city development

HCM City speeds up sub-projects for smart city development

HCM City is speeding up the progress of key sub-projects under the project to turn the city into a smart city from 2017 to 2020 with a vision to 2025.

Foreign experts come to speed up HCM City metro project

Foreign experts come to speed up HCM City metro project

More foreign experts have come to HCM City to hasten a local metro project which is expected to have its first train arrive in October.