A toll plaza on the toll road Hanoi-Bac Giang Expressway. 

 

That was the main content of a conclusion document released after a Government meeting earlier this year to review the project that aims to bring transparency to the currently controversial funding model of Build-Operate-Transfer (BOT) in use in Vietnam.

The ETC project was launched in November 2014 with original total investment of more than VND2 trillion (US$87.6 million).

Implementation of the ETC to replace manual toll booths was deemed necessary by the National Assembly and Prime Minister to create transparency and convenience for road users, as well as ensure traffic order and safety.

The project consisted of two phases.

The first phase was supposed to be implemented by the State-run Vietnam Electronic Toll Collection Company (VETC) at 44 booths, 26 of which are on a section of the trans-Vietnam Ho Chi Minh Highway passing through the Central Highlands, and the rest on other expressways and national highways.

A joint venture of Viettel and other tech enterprises will carry out the second phase at 33 other toll booths.

The system was meant to be in place at all booths nationwide by December 12, 2019.

But as of late last year, the VETC had signed contracts with only 11 of 44 booths as BOT investors were reluctant to hand over lanes to make room for the installation of ETC toll booths.

The main reason for the delay was that profit-sharing rates had not been settled between the VETC and BOT investors.

“This had adversely affected the implementation of the entire system and led to negative feedback from the public,” said the document.

In response, the Government has asked the MoT to clarify exactly who it was that is chiefly responsible for the delay.

March deadline

The Government said the ETC project still needed to be completed by the MoT and relevant agencies and localities.

In order to accelerate the implementation, the Government requested the MoT to immediately install and operate equipment to avoid financial losses.

The ministry and other relevant agencies were also instructed to report to the PM by the end of March, including difficulties, obstacles and proposed plans for the project.

The Committee of State Capital Management was co-ordinating with the MoT to handle any obstacles immediately, the document said. — VNS

Automatic toll collection project will continue

Automatic toll collection project will continue

The Ministry of Transport (MoT) wants to proceed with automatic toll collection on highways, despite the project's main investor seeking to pull out.

DRVN asked to lift a suspension on fee collection at four BOT projects

DRVN asked to lift a suspension on fee collection at four BOT projects

Deputy Minister of Transport Le Dinh Tho on Monday asked the Directorate for Roads of Viet Nam (DRVN) to lift the suspension on fee collection at four BOT (build – operate – transfer) projects.