Cat Linh-Ha Dong Metro Line



The line was supposed to be opened during the Reunification Holiday. However, the Ministry of Transport said that the ACT-French safety consultants issued the system safety certification for the project on April 29. The state council for examination and acceptance of construction works can only issue the final decision based on this certificate.

According to the ministry, after receiving the certification, they immediately submit it but the council will only be able to review and issue their decision after the holiday. After receiving the decision, Hanoi People's Committee and the contractor complete the procedures for the line's commercial operation.

The line has been completed and equipment has been installed. The Railway Project Management Unit and Hanoi Metro Company started transferring documents and assets since early April.

The Ministry of Transport and the Hanoi People's Committee estimated that the metro line would be opened for Reunification Day and May Day in the report to the prime minister. The Ministry of Transport stated that the construction had been completed and all is left is to check and take over documents and procedures.

Dtinews

Cat Linh - Ha Dong urban railway trains to arrive every 6 minutes

Cat Linh - Ha Dong urban railway trains to arrive every 6 minutes

When Hanoi’s Cat Linh - Ha Dong urban railway project is put into operation, every 6-10 minutes there will be a train arriving at the stations to pick up and drop off passengers.