Runway 25R at the Tan Son Nhat International Airport in HCMC will be put into operation on January 10 after six months of renovation, said a representative of Cuu Long Corporation for Investment Development and Project Management of Infrastructure, under the Transport Ministry.

The project’s first phase, which is upgrading the runway, has reached completion. In the second phase, taxiways will undergo renovation, according to the ministry.

The ministry had assigned a consortium including the Civil Engineering Construction Corporation No.4, the Airport Construction Corporation and the 647 Aeronautics Project Construction JSC to implement the project.

Another consortium comprising the Sub-Institute of Transport Science and Technology in Southern Vietnam and the Transport Engineering and Design Inc. South worked as monitoring and consulting contractors for the project.

 

SGT

Long Thanh airport plays part in making Vietnam stronger: PM

Long Thanh airport plays part in making Vietnam stronger: PM

The airport system, including Long Thanh International Airport, will play a significant part in making Vietnam stronger in the coming time, Prime Minister Nguyen Xuan Phuc said on January 5.